Project timeline — CIAL D&B Ads Management

Version: 1.1 · Cut-off date: 2026-05-27 Period covered: 12 weeks (2026-05-18 → 2026-08-07). Mode: Q2–Q3 pilot with two campaigns (CIAL360 Credit + Compliance landing). Operating policy: Client confirms OK on shifts; this timeline is living planning, re-baselined at the close of every sprint.


1. Summary view — phases and weeks

# Phase Start End Duration Closing milestone
1 Discovery & validation Wk 1 (May 18) Wk 2 (May 29) 2 wks Discovery sign-off
2 Technical setup Wk 2 (May 25) Wk 4 (Jun 12) 3 wks End-to-end tracking validated
3 Landings — copy and build Wk 3 (Jun 1) Wk 6 (Jun 26) 4 wks Landings published on staging
4 Creatives and ad copy Wk 4 (Jun 8) Wk 6 (Jun 26) 3 wks Creative set + copy approved
5 QA and pre-launch Wk 6 (Jun 22) Wk 7 (Jul 3) 2 wks Full checklist + go/no-go
6 Pilot launch Wk 7 (Jun 29) Wk 8 (Jul 10) 2 wks Campaigns active and stabilized
7 Iterative optimization Wk 8 (Jul 6) Wk 12 (Aug 7) 5 wks Migration to Smart Bidding where applicable
8 Reporting and Q4 plan Wk 12 (Aug 3) Wk 12 (Aug 7) 1 wk Executive report + Q4 plan

2. Visual Gantt (Mermaid)

gantt
    title CIAL D&B — 12-week plan (Q2–Q3 2026 pilot)
    dateFormat YYYY-MM-DD
    axisFormat %d-%b
    excludes weekends

    section 1. Discovery
    Kickoff and stakeholder interviews     :a1, 2026-05-18, 5d
    Strategy validation with client        :a2, after a1, 3d
    ABM target account list                :a3, 2026-05-20, 7d

    section 2. Technical setup
    LinkedIn / Google / Meta access        :b1, 2026-05-25, 4d
    GTM + GA4 + LinkedIn Pixel + Meta Pixel:b2, after b1, 6d
    Salesforce → offline conversions       :b3, 2026-06-01, 8d
    Base Looker Studio dashboard           :b4, 2026-06-04, 6d

    section 3. Landings
    Credit copy approved by CIAL           :c1, 2026-06-01, 5d
    Compliance copy approved by CIAL       :c2, 2026-06-01, 7d
    Credit landing build in Webflow        :c3, after c1, 8d
    Compliance landing build in Webflow    :c4, after c2, 10d
    Cross-browser and mobile QA            :c5, 2026-06-22, 5d

    section 4. Creatives and ads
    Dashboard mockups + illustrations      :d1, 2026-06-08, 10d
    LinkedIn copy per angle (A/B/C)        :d2, 2026-06-08, 7d
    Google RSA copy per product            :d3, 2026-06-08, 5d
    Creative + copy approval by CIAL       :d4, 2026-06-22, 5d

    section 5. QA and pre-launch
    End-to-end tracking QA                 :e1, 2026-06-22, 5d
    Upload campaigns in draft              :e2, 2026-06-29, 4d
    Go/no-go meeting                       :e3, milestone, 2026-07-02, 1d

    section 6. Launch
    LinkedIn Credit + Compliance — Live    :f1, 2026-06-29, 5d
    Google Search Non-brand — Live         :f3, 2026-07-06, 5d
    Remarketing Display + Meta — Live      :f4, 2026-07-13, 5d

    section 7. Optimization
    Weekly copy and bid iteration          :g1, 2026-07-13, 21d
    Migration to Smart Bidding (≥30 conv)  :g2, 2026-07-27, 10d
    Hero variant A/B test                  :g3, 2026-07-20, 14d

    section 8. Reporting
    Month-1 executive report               :h1, 2026-07-27, 3d
    Q4 plan + budget reallocation          :h2, 2026-08-03, 5d

The Branded Search campaign is deferred from the initial allocation and can be reactivated with additional budget or after the first optimization cycle.


3. Week-by-week (granular)

Week 1 — 2026-05-18 → 2026-05-22

Category Activity Owner Deliverable
Discovery Official project kickoff with CIAL stakeholders EON + CIAL Kickoff minutes
Discovery 1:1 interviews with CCO, CRO and Commercial Director EON Interview notes
Discovery Validation of this strategy document CIAL Approval or adjustments
Discovery Formal access request (LinkedIn, Google, Meta, Salesforce) CIAL IT Open tickets

Week 2 — 2026-05-25 → 2026-05-29 (in progress)

Category Activity Owner Deliverable
Discovery Discovery close + signed minutes EON + CIAL Discovery minutes
Technical setup GTM container verified; LinkedIn Insight Tag confirmed firing EON Pilot tag spec under EON_PILOT_ prefix
Technical setup Google Ads pilot campaign CIAL360 Credit - MX - 2026 Q2 - Search Non-brand created and paused EON Campaign ID 23883887275
Technical setup LinkedIn pilot Ad Set LIA Credit Prospecting - 2026Q2 created in Draft EON Ad Set ID 739402054
Technical setup Lookalike seed list CIALDB_LAL_2026-05-25 uploaded EON LinkedIn processing
Ads — Credit RSA #2 built for Credit Non-brand (15 headlines + 4 descriptions, risk + D&B credibility angle). RSA #1 baseline at 9 of 15 headlines pending completion. EON See Weekly update — May 25–27
Budget Daily budget set to MXN 300/day on Credit Non-brand (MXN 9,000/month) EON Budget aligned with pilot allocation
Pending Page-level "Sponsored Content Poster" permission for LinkedIn ad publication CIAL Page Super Admin Required to publish ads
Discovery ABM list v1 (500 Credit accounts + 500 Compliance accounts) CIAL Sales CSV delivered

Week 3 — 2026-06-01 → 2026-06-05

Category Activity Owner Deliverable
Technical setup Salesforce → offline conversions (lead status sync) CIAL IT + EON Integration working with test data
Technical setup Looker Studio dashboard v1 (base structure) EON Dashboard URL
Landings Credit copy approved by CIAL Marketing CIAL Marketing Written approval
Landings Compliance copy approved by CIAL Marketing + Compliance CIAL Marketing + Compliance Written approval

Week 4 — 2026-06-08 → 2026-06-12

Category Activity Owner Deliverable
Technical setup End-to-end tracking QA (events reaching GA4 and Salesforce) EON QA report
Landings Credit landing build in Webflow EON / Webflow vendor Landing on staging
Landings Compliance landing build in Webflow (both sections) EON / Webflow vendor Landing on staging
Creatives Mockup brief and visual-asset production EON Signed brief
Creatives LinkedIn ad copy by angle A/B/C (Credit + Compliance) EON Drafts in shared doc

Week 5 — 2026-06-15 → 2026-06-19

Category Activity Owner Deliverable
Landings UX refinement (mobile + desktop) EON Landings v2 on staging
Creatives Production of visuals and dashboard mockups EON Design Set delivered in Figma
Creatives Google RSA copy (15 headlines + 4 descriptions per product) EON Drafts in shared doc

Week 6 — 2026-06-22 → 2026-06-26

Category Activity Owner Deliverable
Landings Final cross-browser and mobile QA EON Approved QA report
Landings Production publication of both landings EON + CIAL Webflow Public URLs
Creatives Final creative approval by CIAL CIAL Marketing Written approval
Pre-launch Upload campaigns to LinkedIn and Google Ads in draft EON Draft screenshots
Pre-launch Tracking QA in real conditions (test form submission) EON Report

Week 7 — 2026-06-29 → 2026-07-03

Category Activity Owner Deliverable
Pre-launch Go/no-go meeting EON + CIAL Approval minutes
Launch LinkedIn Ads go-live (Credit + Compliance Prospecting) EON Active campaigns
Launch Google Search Non-brand go-live (Credit + Compliance) EON Active campaigns
Operations Daily monitoring of delivery, CPL and QS EON Internal daily standup

Week 8 — 2026-07-06 → 2026-07-10

Category Activity Owner Deliverable
Operations First optimization round: pause keywords without traction EON Changelog
Operations Lead-quality validation with CIAL Sales (MQL quality) CIAL Sales + EON Quality report
Reporting Mid-month checkin with client EON Minutes

Week 9 — 2026-07-13 → 2026-07-17

Category Activity Owner Deliverable
Launch Remarketing go-live (Display + YouTube + Meta) EON Active campaigns
Optimization A/B hero test (Variant A vs B vs C) per product EON Test configuration
Optimization Bid adjustment week 1 (max delta 20%) EON Changelog

Week 10 — 2026-07-20 → 2026-07-24

Category Activity Owner Deliverable
Optimization Quality Score analysis and rewrite of ad groups with QS<6 EON Changelog
Optimization LinkedIn creative refresh (fatigue) EON Set v2 published
Reporting Weekly status report EON PDF

Week 11 — 2026-07-27 → 2026-07-31

Category Activity Owner Deliverable
Optimization Migration to Smart Bidding (campaigns with ≥30 conversions) EON Changelog
Optimization Pause keywords with CPA > 2× target EON Changelog
Reporting Month-1 executive report EON PDF + session with CIAL

Week 12 — 2026-08-03 → 2026-08-07

Category Activity Owner Deliverable
Reporting Q2–Q3 pilot close meeting EON + CIAL Minutes + decisions
Q4 plan Budget reallocation by channel and product EON Q4 plan proposal
Q4 plan LATAM expansion roadmap (Colombia, Peru, Chile) EON Roadmap proposal

4. Key milestones

# Milestone Week Target date
M1 Discovery closed and validated 2 2026-05-29
M2 End-to-end tracking validated 4 2026-06-12
M3 Landings published in production 6 2026-06-26
M4 Pilot launch 7 2026-06-29
M5 First lead-quality report with CIAL Sales 8 2026-07-10
M6 Month-1 executive report 11 2026-07-31
M7 Q4 plan and budget reallocation 12 2026-08-07

5. Critical dependencies

These dependencies are blocking: if one slips, the timeline shifts.

  1. Platform access (Wks 1–2): without external-admin access to LinkedIn Campaign Manager, Google Ads, and Meta Business, technical setup cannot proceed. Owner: CIAL IT.
  2. LinkedIn Page permission (Wk 2 onward): the "Sponsored Content Poster" role on the CIAL Dun & Bradstreet Company Page is required to publish LinkedIn ads beyond Draft. Owner: CIAL Page Super Admin.
  3. ABM list (Wk 2): without a target-account list there is no matched audience and no Customer Match. Owner: CIAL Sales/Marketing.
  4. Salesforce → offline conversions (Wks 3–4): without this integration, Smart Bidding migration in Wk 11 cannot proceed. Campaigns stay on manual CPC with higher CPL. Owner: CIAL IT + EON.
  5. Approval of ad and landing copy (Wk 6): without written sign-off from CIAL Marketing + Compliance + Legal, campaigns cannot launch. Owner: CIAL.
  6. Lead-quality validation by CIAL Sales (Wk 8): without the qualification loop, automated bidding optimizes for low-quality leads. Owner: CIAL Sales.

6. Buffer and slippage policy

  • Each phase carries an implicit 20% buffer (already included in the durations).
  • If a critical dependency slips by more than 3 business days, EON issues a change note that updates this timeline and moves subsequent milestones.
  • The client stated that they prioritize visibility over speed: date changes are acceptable as long as they are documented.

Document maintained by EON · Next update at the close of every bi-weekly sprint.